Quandel to manage construction on $47M Geisinger expansion

By - Last modified: October 29, 2012 at 11:55 AM

Back to Top Comments Print

Harrisburg-based Quandel Construction Group Inc. will be the construction manager for Geisinger Health System's $47 million expansion of its Woodbine Medical Clinic.

Montour County-based Geisinger is adding about 132,000 square feet of clinical, therapy and food-service space at the Woodbine office building on its main campus in Danville.

Quandel said it’s working on preconstruction services with Philadelphia-based design firm EwingCole for the project that’s expected to break ground in the spring and be completed in late 2014.

The construction company is also the manager for Harrisburg-based PinnacleHealth System’s $100 million West Shore Hospital being built in Cumberland County, also scheduled to be complete in 2014.

Quandel has worked on seven projects for Geisinger’s main campus and 16 overall for the group.

 

Jim T. Ryan

Jim T. Ryan

Jim T. Ryan covers Cumberland County, manufacturing, distribution, transportation and logistics. Have a tip or question for him? Email him at jimr@cpbj.com. Follow him on Twitter, @JimTRyanCPBJ.